Shooting schedule and equipment list


Introduction

This blog post will include the information of a shooting schedule and the equipment list for our 5 minute single camera production.

Equipment list & Location

We have decided to shoot our 5 minute single camera product in a desolate house, which we have got permission to use. Our deadline for the project is Thursday 28th March 2013, so we need to get filming done asap (hopefully by next week - 14/03/2013) to make sure that we fit in enough time for post-production elements and editing.

The equipment and props that we need are;

HD Canon camera and charger
SD memory card and reader
Tripod
Apple mac
Microphones/boompoles
Regular home items, e.g. chair, table, etc

We have decided that we do not want to use any artificial lighting, e.g. key, filler or back lighting as we want our film to have a dark and eerie natural feel. So we are going to be relying on the natural lighting around us to film.

Shooting schedule


Date
Task
What needs to be done
14/02/2013
Pre - production
Do research on existing short films and analyse to gather ideas

Carried out tasks like;
-analysis of existing films
21/02/2013
Pre - production
Brainstorm ideas for 5 minute production. Add structure to our idea.

Carried out tasks like;
-Story board
-mind maps
-considering target audience
-word/mood board
28/02/2013
Pre - production
Carry out various pre-production tasks.

Carry out tasks like;
-treatment/proposal
-music/sounds
-looking and asking for permission for location space and models
-collecting and gathering props
07/03/2013
Pre - production
Carry out various pre-production tasks. Got permission for location and models.

Carry out tasks like;
-considering locations
-finding actors/actresses
-risk assessments
-working out the budget
14/03/2013
Production
Filming

Carry out tasks like;
-Setting up
-getting the actors ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks
21/03/2013
Production
Filming

Carry out tasks like;
-Setting up
-getting the actors ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks
28/03/2013
Production
Filming

Carry out tasks like;
-Setting up
-getting the actors ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks
04/04/2013
Holidays
11/04/2013
Holidays
18/04/2013
Post -production
Must finish off final editing and evaluations. Deadline
Carry out tasks like;
-editing clips
-evaluation
25/04/2013
Post-production
Must finish off final editing and evaluations. Deadline
Carry out tasks like;
-editing clips
-evaluation





The shooting schedule does not include any out of hours filming or work. Tasks will also be carried out throughout the week to ensure we keep on top of our schedule.