Introduction
This blog post will include the information of a shooting schedule and the equipment list for our 5 minute single camera production.
Equipment list & Location
We have decided to shoot our 5 minute single camera product in a desolate house, which we have got permission to use. Our deadline for the project is Thursday 28th March 2013, so we need to get filming done asap (hopefully by next week - 14/03/2013) to make sure that we fit in enough time for post-production elements and editing.
The equipment and props that we need are;
HD Canon camera and charger
SD memory card and reader
Tripod
Apple mac
Microphones/boompoles
Regular home items, e.g. chair, table, etc
We have decided that we do not want to use any artificial lighting, e.g. key, filler or back lighting as we want our film to have a dark and eerie natural feel. So we are going to be relying on the natural lighting around us to film.
Shooting schedule
Date
|
Task
|
What needs to be done
|
14/02/2013
|
Pre - production
|
Do research on existing short films and analyse to gather
ideas
Carried out tasks like;
-analysis of existing films
|
21/02/2013
|
Pre - production
|
Brainstorm ideas for 5 minute production. Add structure to
our idea.
Carried out tasks like;
-Story board
-mind maps
-considering target audience
-word/mood board
|
28/02/2013
|
Pre - production
|
Carry out various pre-production tasks.
Carry out tasks like;
-treatment/proposal
-music/sounds
-looking and asking for permission for location space and
models
-collecting and gathering props
|
07/03/2013
|
Pre - production
|
Carry out various pre-production tasks. Got permission for
location and models.
Carry out tasks like;
-considering locations
-finding actors/actresses
-risk assessments
-working out the budget
|
14/03/2013
|
Production
|
Filming
Carry out tasks like;
-Setting up
-getting the actors ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks
|
21/03/2013
|
Production
|
Filming
Carry out tasks like;
-Setting up
-getting the actors ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks
|
28/03/2013
|
Production
|
Filming
Carry out tasks like;
-Setting up
-getting the actors ready and revised of the scene
-directing and recording scenes
-being aware of health and safety risks
|
04/04/2013
|
Holidays
|
|
11/04/2013
|
Holidays
|
|
18/04/2013
|
Post -production
|
Must finish off final editing and evaluations. Deadline
Carry out tasks like;
-editing clips
-evaluation
|
25/04/2013
|
Post-production
|
Must finish off final editing and evaluations. Deadline
Carry out tasks like;
-editing clips
-evaluation
|
|
|
|
The shooting schedule does not include any out of hours filming or work. Tasks will also be carried out throughout the week to ensure we keep on top of our schedule.